Tuesday, September 17

Tag: Calculate Total Cost In Excel

Calculate Total Cost Of Your Project On Hourly Rate

Calculate Total Cost Of Your Project On Hourly Rate

Date And Time, FORMULAS
Suppose For Example If There Are 10 Workers At A Construction Plant And Spend 10 Workdays And 8 Working Hours Per Day To Complete. Then To Find The Cost By Hours We Will First Need To Find The Total Number Of Hours. That Is ( Total Workers * Total Working Days * Total Working Hours / Day ). Once We have The Total Number Of Hours We Can Multiply It By Our Hourly Rate. Formula For Full Project Cost :- =A7*B7*C7*D7 Formula For Per Day Cost :- =(A3*B3*C3*D3) /C3 Formula For Per Person Cost :- =(A3*B3*C3*D3) /A3 Formula For Per Hour Cost :- =D3*A3